November 19, 2026
On October 2, Gov. Ron DeSantis cut the ribbon on the River Road widening, which turned five miles of State Road 777 between U.S. 41 and I-75 from two lanes into six. FDOT's announcement describes it as a $61 million investment shared by the state and Sarasota County. The department's project page lists the construction cost alone at $47.5 million. Six weeks later, the road is part of everyday driving in Wellen Park. There are three lanes in each direction and traffic signals at West Villages Parkway, Center Road and East Venice Avenue.
The new lanes run in one direction from the community. Head north from U.S. 41 toward the interstate and the whole route is new road. Head south on River Road toward Englewood and you are still on two lanes. The county's plan to widen that part has a construction start in 2027. The trips that changed this fall are the ones going north.
The Florida Department of Transportation's announcement says the project triples the road's capacity. It lists several changes beyond the extra lanes that a driver, walker or cyclist will notice:
At the ceremony, Gov. Ron DeSantis said the project was finished ahead of schedule. As WGCU reported, he described the underpasses this way:
"We've also added two new wildlife underpasses, which have been proven to cut down on wildlife collisions in other parts of the state where they have been implemented."
The six lanes north of Center Road were not in the original plan. When FDOT presented the design-build project in January 2022, it called for six lanes from U.S. 41 to Center Road and four lanes from Center Road to I-75. In November 2024, FDOT held a public hearing on adding one more lane in each direction on the Center Road to I-75 section. That decision made the whole corridor six lanes. According to the department's October 2024 reevaluation, the extra lanes were built inside the median, so no additional right-of-way was needed.
The reevaluation's traffic projections show why FDOT wanted the extra lanes. One design sheet counts about 28,241 vehicles a day on the corridor in 2021 and projects 48,715 a day by 2043. A second sheet goes from 27,376 to 45,216 over the same years. Either way, FDOT expects daily traffic to grow by roughly 65 to 72 percent over two decades. The road that opened this fall was sized for that future traffic, not for today's.
The ribbon cutting marked the finished roadway. Some smaller work is still going on. The Daily Sun's report on the opening listed thermoplastic striping, drainage repairs and other punch-list items still to be done, plus cabbage palms that had been delivered and were waiting to be planted. FDOT's project page still estimates the current phase will be complete in early 2027. In early November, the Sarasota/Manatee MPO's traffic update listed maintenance, erosion-control and closeout work on SR 777 between I-75 and U.S. 41.
For drivers, that means occasional work crews along the shoulders and medians through the winter, on a road whose travel lanes are all open.
The FDOT corridor ends at U.S. 41. South of there, River Road is a county road and a separate project. Sarasota County plans to widen South River Road to four lanes from U.S. 41 to Winchester Boulevard, then Winchester Boulevard from South River Road to the Charlotte County line. The county's April 22, 2026 transportation workshop called it a 7.2-mile project with an $88 million construction cost estimate.
| Item | Timing as reported | Source |
|---|---|---|
| Design | Workshop target of mid-2026; the Daily Sun later reported design 90% complete | Sarasota County workshop, April 22, 2026; Daily Sun report |
| Construction start | Late 2027 | Sarasota County workshop, April 22, 2026 |
| Construction start | Spring 2027 | Daily Sun report |
| Construction finish | Summer 2029 | Daily Sun report |
| South River Road and Winchester Boulevard intersection | Construction to begin late 2026 with federal funding | Sarasota County workshop, April 22, 2026 |
The intersection project is the closest of these. Sarasota County advertised it for bid this spring, with submissions due May 27, 2026. One change on the south side is already in place. The temporary signal at South River Road and Manasota Beach Road is working, and the Daily Sun reported that the new intersection connection has opened along with it.
One section of South River Road is not part of the four-lane project. It is the roughly two-mile stretch from Winchester Boulevard to the intersection of Pine Street and East Dearborn Street. Along it are a post office, the Englewood Sports Complex and Morris Industrial Park.
Sarasota County public information officer Emily Blaine told the Daily Sun that the county's long-range thoroughfare plan calls for widening this section from two undivided lanes to four divided lanes. She said it is not in the county's five-year capital improvement program, so it has no construction funding for at least that long. Even after the 2027 to 2029 project is done, a drive from Wellen Park to downtown Englewood on River Road will end on two-lane road.
Taken together, here is what each common River Road trip from Wellen Park looks like as of this week:
The 2027 Braves spring training season will be the first since River Road was finished. Our look at the 2027 Braves schedule explains how game-day traffic already moves through the community, and this season visitors coming in from I-75 will drive the six-lane road.
At NextHome Suncoast, we keep track of how roads like River Road change the daily drives from Wellen Park, North Port and Englewood. If a commute, a beach run or a spring training drive is part of your next move, let's talk it through and find your Suncoast lifestyle together.
Stay up to date on the latest real estate trends.
Whether buying or selling, our team is here to provide a seamless, elevated experience every step of the way. Reach out today to start the conversation.